Japan Times: Real cost of Fukushima disaster will reach $626 billion — triple the government’s estimate

Informaciones

By: Japan Times

Real cost of Fukushima disaster will reach ¥70 trillion, or triple government’s estimate: think tank

A Tokyo-based think tank estimates that the complete cost of dealing with the Fukushima disaster could reach ¥70 trillion. | KYODO

 

A private think tank says the total cost of the Fukushima disaster could reach ¥70 trillion ($626 billion), or more than three times the government’s latest estimate.
In a study Saturday, the Japan Center for Economic Research said costs of dealing with the heavily damaged Fukushima No. 1 nuclear plant run by Tokyo Electric Power Company Holdings Inc. could rise to between ¥50 trillion and ¥70 trillion.
In December, the government estimated the costs would reach roughly ¥22 trillion.
“If costs rise, the public burden could greatly increase. The country’s nuclear policy needs to be reviewed,” JCER said.
The government’s initial expectations pegged the costs at ¥11 trillion.
But a study by the Ministry of Economy, Trade and Industry said that the final figure could turn out to be double the sum estimated in 2013.
Following that, the government decided to raise electricity rates to secure the money needed to cover compensation payments to the evacuees.
According to METI’s estimates, the bill for compensation payments will be ¥8 trillion, a figure the JCER decided to adopt.
The JCER, however, estimates the cost of the decontamination work will hit ¥30 trillion, or five times more than the government’s estimate of ¥6 trillion. The think tank based this calculation on a presumption that radioactive substances will be disposed of at a nuclear facility in the village of Rokkasho in Aomori Prefecture.
The government is seeking a way to treat radioactive soil and other waste in Fukushima Prefecture that could grow to roughly 22 million cu. meters, but where and how to dispose of it has yet to be decided.
Costs related to this procedure are not included in the government’s calculations.
In the meantime, JCER estimates that the cost of decommissioning the crippled reactors, which is expected to take 30 to 40 years, will reach ¥11 trillion. The government’s estimate is ¥8 trillion.
JCER also estimates that treating the contaminated water stored in hundreds of tanks at the plant will cost ¥20 trillion unless it is dumped into the ocean after being diluted as recommended by regulators.
Pourquoi le nucléaire est en train de ruiner la France Russian nuclear facility denies it is source of high radioactivity levels

Related Posts

Energia solar está prestes a atingir 100 gigawatts graças à China

Informaciones

Energia solar está prestes a atingir 100 gigawatts graças à China

A indústria de energia solar está prestes a atingir um marco: as instalações globais deverão atingir 108 gigawatts este ano graças à China, mostram projeções da IHS Markit.

Will Cheap Renewables Make Nuclear Power Obsolete?

Informaciones

Will Cheap Renewables Make Nuclear Power Obsolete?

Cheap renewables are mounting a serious challenge to nuclear power, which in 2017 has had a difficult year. Key projects have been abandoned, costs are rising, and politicians in countries which previously championed the industry are withdrawing their support.

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

Informaciones

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

La compagnie japonaise d’électricité Kansai Electric Power a officialisé vendredi la fermeture en 2019 de deux de ses réacteurs nucléaires vieillissants. Elle juge trop élevé le coût de leur mise en conformité avec les nouvelles normes de sécurité post-Fukushima.

Étiquettes

Canada Canada Canada Canada Canada Canada France France France France France France France France Fukushima Fukushima Fukushima Fukushima Fukushima Fukushima Fukushima Fukushima Nuclear Nuclear Nuclear Nuclear Nuclear Nuclear Nuclear Nuclear Nuclear Nuclear safety safety safety safety safety safety safety safety United States United States United States United States United States
See all tags
novembre 3, 2017

Japan Times: Real cost of Fukushima disaster will reach $626 billion — triple the government’s estimate

Informações

By: Japan Times

Real cost of Fukushima disaster will reach ¥70 trillion, or triple government’s estimate: think tank

A Tokyo-based think tank estimates that the complete cost of dealing with the Fukushima disaster could reach ¥70 trillion. | KYODO

 

A private think tank says the total cost of the Fukushima disaster could reach ¥70 trillion ($626 billion), or more than three times the government’s latest estimate.
In a study Saturday, the Japan Center for Economic Research said costs of dealing with the heavily damaged Fukushima No. 1 nuclear plant run by Tokyo Electric Power Company Holdings Inc. could rise to between ¥50 trillion and ¥70 trillion.
In December, the government estimated the costs would reach roughly ¥22 trillion.
“If costs rise, the public burden could greatly increase. The country’s nuclear policy needs to be reviewed,” JCER said.
The government’s initial expectations pegged the costs at ¥11 trillion.
But a study by the Ministry of Economy, Trade and Industry said that the final figure could turn out to be double the sum estimated in 2013.
Following that, the government decided to raise electricity rates to secure the money needed to cover compensation payments to the evacuees.
According to METI’s estimates, the bill for compensation payments will be ¥8 trillion, a figure the JCER decided to adopt.
The JCER, however, estimates the cost of the decontamination work will hit ¥30 trillion, or five times more than the government’s estimate of ¥6 trillion. The think tank based this calculation on a presumption that radioactive substances will be disposed of at a nuclear facility in the village of Rokkasho in Aomori Prefecture.
The government is seeking a way to treat radioactive soil and other waste in Fukushima Prefecture that could grow to roughly 22 million cu. meters, but where and how to dispose of it has yet to be decided.
Costs related to this procedure are not included in the government’s calculations.
In the meantime, JCER estimates that the cost of decommissioning the crippled reactors, which is expected to take 30 to 40 years, will reach ¥11 trillion. The government’s estimate is ¥8 trillion.
JCER also estimates that treating the contaminated water stored in hundreds of tanks at the plant will cost ¥20 trillion unless it is dumped into the ocean after being diluted as recommended by regulators.
Pourquoi le nucléaire est en train de ruiner la France Russian nuclear facility denies it is source of high radioactivity levels

Related Posts

Energia solar está prestes a atingir 100 gigawatts graças à China

Informações

Energia solar está prestes a atingir 100 gigawatts graças à China

A indústria de energia solar está prestes a atingir um marco: as instalações globais deverão atingir 108 gigawatts este ano graças à China, mostram projeções da IHS Markit.

Will Cheap Renewables Make Nuclear Power Obsolete?

Informações

Will Cheap Renewables Make Nuclear Power Obsolete?

Cheap renewables are mounting a serious challenge to nuclear power, which in 2017 has had a difficult year. Key projects have been abandoned, costs are rising, and politicians in countries which previously championed the industry are withdrawing their support.

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

Informações

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

La compagnie japonaise d’électricité Kansai Electric Power a officialisé vendredi la fermeture en 2019 de deux de ses réacteurs nucléaires vieillissants. Elle juge trop élevé le coût de leur mise en conformité avec les nouvelles normes de sécurité post-Fukushima.

novembre 3, 2017

Japan Times: Real cost of Fukushima disaster will reach $626 billion — triple the government’s estimate

Без категории

By: Japan Times

Real cost of Fukushima disaster will reach ¥70 trillion, or triple government’s estimate: think tank

A Tokyo-based think tank estimates that the complete cost of dealing with the Fukushima disaster could reach ¥70 trillion. | KYODO

 

A private think tank says the total cost of the Fukushima disaster could reach ¥70 trillion ($626 billion), or more than three times the government’s latest estimate.
In a study Saturday, the Japan Center for Economic Research said costs of dealing with the heavily damaged Fukushima No. 1 nuclear plant run by Tokyo Electric Power Company Holdings Inc. could rise to between ¥50 trillion and ¥70 trillion.
In December, the government estimated the costs would reach roughly ¥22 trillion.
“If costs rise, the public burden could greatly increase. The country’s nuclear policy needs to be reviewed,” JCER said.
The government’s initial expectations pegged the costs at ¥11 trillion.
But a study by the Ministry of Economy, Trade and Industry said that the final figure could turn out to be double the sum estimated in 2013.
Following that, the government decided to raise electricity rates to secure the money needed to cover compensation payments to the evacuees.
According to METI’s estimates, the bill for compensation payments will be ¥8 trillion, a figure the JCER decided to adopt.
The JCER, however, estimates the cost of the decontamination work will hit ¥30 trillion, or five times more than the government’s estimate of ¥6 trillion. The think tank based this calculation on a presumption that radioactive substances will be disposed of at a nuclear facility in the village of Rokkasho in Aomori Prefecture.
The government is seeking a way to treat radioactive soil and other waste in Fukushima Prefecture that could grow to roughly 22 million cu. meters, but where and how to dispose of it has yet to be decided.
Costs related to this procedure are not included in the government’s calculations.
In the meantime, JCER estimates that the cost of decommissioning the crippled reactors, which is expected to take 30 to 40 years, will reach ¥11 trillion. The government’s estimate is ¥8 trillion.
JCER also estimates that treating the contaminated water stored in hundreds of tanks at the plant will cost ¥20 trillion unless it is dumped into the ocean after being diluted as recommended by regulators.
Pourquoi le nucléaire est en train de ruiner la France Russian nuclear facility denies it is source of high radioactivity levels

Related Posts

Energia solar está prestes a atingir 100 gigawatts graças à China

Без категории

Energia solar está prestes a atingir 100 gigawatts graças à China

A indústria de energia solar está prestes a atingir um marco: as instalações globais deverão atingir 108 gigawatts este ano graças à China, mostram projeções da IHS Markit.

Will Cheap Renewables Make Nuclear Power Obsolete?

Без категории

Will Cheap Renewables Make Nuclear Power Obsolete?

Cheap renewables are mounting a serious challenge to nuclear power, which in 2017 has had a difficult year. Key projects have been abandoned, costs are rising, and politicians in countries which previously championed the industry are withdrawing their support.

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

Без категории

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

La compagnie japonaise d’électricité Kansai Electric Power a officialisé vendredi la fermeture en 2019 de deux de ses réacteurs nucléaires vieillissants. Elle juge trop élevé le coût de leur mise en conformité avec les nouvelles normes de sécurité post-Fukushima.

novembre 3, 2017

Japan Times: Real cost of Fukushima disaster will reach $626 billion — triple the government’s estimate

カテゴリーなし

By: Japan Times

Real cost of Fukushima disaster will reach ¥70 trillion, or triple government’s estimate: think tank

A Tokyo-based think tank estimates that the complete cost of dealing with the Fukushima disaster could reach ¥70 trillion. | KYODO

 

A private think tank says the total cost of the Fukushima disaster could reach ¥70 trillion ($626 billion), or more than three times the government’s latest estimate.
In a study Saturday, the Japan Center for Economic Research said costs of dealing with the heavily damaged Fukushima No. 1 nuclear plant run by Tokyo Electric Power Company Holdings Inc. could rise to between ¥50 trillion and ¥70 trillion.
In December, the government estimated the costs would reach roughly ¥22 trillion.
“If costs rise, the public burden could greatly increase. The country’s nuclear policy needs to be reviewed,” JCER said.
The government’s initial expectations pegged the costs at ¥11 trillion.
But a study by the Ministry of Economy, Trade and Industry said that the final figure could turn out to be double the sum estimated in 2013.
Following that, the government decided to raise electricity rates to secure the money needed to cover compensation payments to the evacuees.
According to METI’s estimates, the bill for compensation payments will be ¥8 trillion, a figure the JCER decided to adopt.
The JCER, however, estimates the cost of the decontamination work will hit ¥30 trillion, or five times more than the government’s estimate of ¥6 trillion. The think tank based this calculation on a presumption that radioactive substances will be disposed of at a nuclear facility in the village of Rokkasho in Aomori Prefecture.
The government is seeking a way to treat radioactive soil and other waste in Fukushima Prefecture that could grow to roughly 22 million cu. meters, but where and how to dispose of it has yet to be decided.
Costs related to this procedure are not included in the government’s calculations.
In the meantime, JCER estimates that the cost of decommissioning the crippled reactors, which is expected to take 30 to 40 years, will reach ¥11 trillion. The government’s estimate is ¥8 trillion.
JCER also estimates that treating the contaminated water stored in hundreds of tanks at the plant will cost ¥20 trillion unless it is dumped into the ocean after being diluted as recommended by regulators.
Pourquoi le nucléaire est en train de ruiner la France Russian nuclear facility denies it is source of high radioactivity levels

Related Posts

Energia solar está prestes a atingir 100 gigawatts graças à China

カテゴリーなし

Energia solar está prestes a atingir 100 gigawatts graças à China

A indústria de energia solar está prestes a atingir um marco: as instalações globais deverão atingir 108 gigawatts este ano graças à China, mostram projeções da IHS Markit.

Will Cheap Renewables Make Nuclear Power Obsolete?

カテゴリーなし

Will Cheap Renewables Make Nuclear Power Obsolete?

Cheap renewables are mounting a serious challenge to nuclear power, which in 2017 has had a difficult year. Key projects have been abandoned, costs are rising, and politicians in countries which previously championed the industry are withdrawing their support.

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

カテゴリーなし

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

La compagnie japonaise d’électricité Kansai Electric Power a officialisé vendredi la fermeture en 2019 de deux de ses réacteurs nucléaires vieillissants. Elle juge trop élevé le coût de leur mise en conformité avec les nouvelles normes de sécurité post-Fukushima.

novembre 3, 2017

Japan Times: Real cost of Fukushima disaster will reach $626 billion — triple the government’s estimate

Informations

By: Japan Times

Real cost of Fukushima disaster will reach ¥70 trillion, or triple government’s estimate: think tank

A Tokyo-based think tank estimates that the complete cost of dealing with the Fukushima disaster could reach ¥70 trillion. | KYODO

 

A private think tank says the total cost of the Fukushima disaster could reach ¥70 trillion ($626 billion), or more than three times the government’s latest estimate.
In a study Saturday, the Japan Center for Economic Research said costs of dealing with the heavily damaged Fukushima No. 1 nuclear plant run by Tokyo Electric Power Company Holdings Inc. could rise to between ¥50 trillion and ¥70 trillion.
In December, the government estimated the costs would reach roughly ¥22 trillion.
“If costs rise, the public burden could greatly increase. The country’s nuclear policy needs to be reviewed,” JCER said.
The government’s initial expectations pegged the costs at ¥11 trillion.
But a study by the Ministry of Economy, Trade and Industry said that the final figure could turn out to be double the sum estimated in 2013.
Following that, the government decided to raise electricity rates to secure the money needed to cover compensation payments to the evacuees.
According to METI’s estimates, the bill for compensation payments will be ¥8 trillion, a figure the JCER decided to adopt.
The JCER, however, estimates the cost of the decontamination work will hit ¥30 trillion, or five times more than the government’s estimate of ¥6 trillion. The think tank based this calculation on a presumption that radioactive substances will be disposed of at a nuclear facility in the village of Rokkasho in Aomori Prefecture.
The government is seeking a way to treat radioactive soil and other waste in Fukushima Prefecture that could grow to roughly 22 million cu. meters, but where and how to dispose of it has yet to be decided.
Costs related to this procedure are not included in the government’s calculations.
In the meantime, JCER estimates that the cost of decommissioning the crippled reactors, which is expected to take 30 to 40 years, will reach ¥11 trillion. The government’s estimate is ¥8 trillion.
JCER also estimates that treating the contaminated water stored in hundreds of tanks at the plant will cost ¥20 trillion unless it is dumped into the ocean after being diluted as recommended by regulators.
Pourquoi le nucléaire est en train de ruiner la France Russian nuclear facility denies it is source of high radioactivity levels

Related Posts

Energia solar está prestes a atingir 100 gigawatts graças à China

Informations

Energia solar está prestes a atingir 100 gigawatts graças à China

A indústria de energia solar está prestes a atingir um marco: as instalações globais deverão atingir 108 gigawatts este ano graças à China, mostram projeções da IHS Markit.

Will Cheap Renewables Make Nuclear Power Obsolete?

Informations

Will Cheap Renewables Make Nuclear Power Obsolete?

Cheap renewables are mounting a serious challenge to nuclear power, which in 2017 has had a difficult year. Key projects have been abandoned, costs are rising, and politicians in countries which previously championed the industry are withdrawing their support.

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

Informations

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

La compagnie japonaise d’électricité Kansai Electric Power a officialisé vendredi la fermeture en 2019 de deux de ses réacteurs nucléaires vieillissants. Elle juge trop élevé le coût de leur mise en conformité avec les nouvelles normes de sécurité post-Fukushima.

novembre 3, 2017

Japan Times: Real cost of Fukushima disaster will reach $626 billion — triple the government’s estimate

Non categorizzato

By: Japan Times

Real cost of Fukushima disaster will reach ¥70 trillion, or triple government’s estimate: think tank

A Tokyo-based think tank estimates that the complete cost of dealing with the Fukushima disaster could reach ¥70 trillion. | KYODO

 

A private think tank says the total cost of the Fukushima disaster could reach ¥70 trillion ($626 billion), or more than three times the government’s latest estimate.
In a study Saturday, the Japan Center for Economic Research said costs of dealing with the heavily damaged Fukushima No. 1 nuclear plant run by Tokyo Electric Power Company Holdings Inc. could rise to between ¥50 trillion and ¥70 trillion.
In December, the government estimated the costs would reach roughly ¥22 trillion.
“If costs rise, the public burden could greatly increase. The country’s nuclear policy needs to be reviewed,” JCER said.
The government’s initial expectations pegged the costs at ¥11 trillion.
But a study by the Ministry of Economy, Trade and Industry said that the final figure could turn out to be double the sum estimated in 2013.
Following that, the government decided to raise electricity rates to secure the money needed to cover compensation payments to the evacuees.
According to METI’s estimates, the bill for compensation payments will be ¥8 trillion, a figure the JCER decided to adopt.
The JCER, however, estimates the cost of the decontamination work will hit ¥30 trillion, or five times more than the government’s estimate of ¥6 trillion. The think tank based this calculation on a presumption that radioactive substances will be disposed of at a nuclear facility in the village of Rokkasho in Aomori Prefecture.
The government is seeking a way to treat radioactive soil and other waste in Fukushima Prefecture that could grow to roughly 22 million cu. meters, but where and how to dispose of it has yet to be decided.
Costs related to this procedure are not included in the government’s calculations.
In the meantime, JCER estimates that the cost of decommissioning the crippled reactors, which is expected to take 30 to 40 years, will reach ¥11 trillion. The government’s estimate is ¥8 trillion.
JCER also estimates that treating the contaminated water stored in hundreds of tanks at the plant will cost ¥20 trillion unless it is dumped into the ocean after being diluted as recommended by regulators.
Pourquoi le nucléaire est en train de ruiner la France Russian nuclear facility denies it is source of high radioactivity levels

Related Posts

Energia solar está prestes a atingir 100 gigawatts graças à China

Non categorizzato

Energia solar está prestes a atingir 100 gigawatts graças à China

A indústria de energia solar está prestes a atingir um marco: as instalações globais deverão atingir 108 gigawatts este ano graças à China, mostram projeções da IHS Markit.

Will Cheap Renewables Make Nuclear Power Obsolete?

Non categorizzato

Will Cheap Renewables Make Nuclear Power Obsolete?

Cheap renewables are mounting a serious challenge to nuclear power, which in 2017 has had a difficult year. Key projects have been abandoned, costs are rising, and politicians in countries which previously championed the industry are withdrawing their support.

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

Non categorizzato

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

La compagnie japonaise d’électricité Kansai Electric Power a officialisé vendredi la fermeture en 2019 de deux de ses réacteurs nucléaires vieillissants. Elle juge trop élevé le coût de leur mise en conformité avec les nouvelles normes de sécurité post-Fukushima.

novembre 3, 2017

Japan Times: Real cost of Fukushima disaster will reach $626 billion — triple the government’s estimate

غير مصنف

By: Japan Times

Real cost of Fukushima disaster will reach ¥70 trillion, or triple government’s estimate: think tank

A Tokyo-based think tank estimates that the complete cost of dealing with the Fukushima disaster could reach ¥70 trillion. | KYODO

 

A private think tank says the total cost of the Fukushima disaster could reach ¥70 trillion ($626 billion), or more than three times the government’s latest estimate.
In a study Saturday, the Japan Center for Economic Research said costs of dealing with the heavily damaged Fukushima No. 1 nuclear plant run by Tokyo Electric Power Company Holdings Inc. could rise to between ¥50 trillion and ¥70 trillion.
In December, the government estimated the costs would reach roughly ¥22 trillion.
“If costs rise, the public burden could greatly increase. The country’s nuclear policy needs to be reviewed,” JCER said.
The government’s initial expectations pegged the costs at ¥11 trillion.
But a study by the Ministry of Economy, Trade and Industry said that the final figure could turn out to be double the sum estimated in 2013.
Following that, the government decided to raise electricity rates to secure the money needed to cover compensation payments to the evacuees.
According to METI’s estimates, the bill for compensation payments will be ¥8 trillion, a figure the JCER decided to adopt.
The JCER, however, estimates the cost of the decontamination work will hit ¥30 trillion, or five times more than the government’s estimate of ¥6 trillion. The think tank based this calculation on a presumption that radioactive substances will be disposed of at a nuclear facility in the village of Rokkasho in Aomori Prefecture.
The government is seeking a way to treat radioactive soil and other waste in Fukushima Prefecture that could grow to roughly 22 million cu. meters, but where and how to dispose of it has yet to be decided.
Costs related to this procedure are not included in the government’s calculations.
In the meantime, JCER estimates that the cost of decommissioning the crippled reactors, which is expected to take 30 to 40 years, will reach ¥11 trillion. The government’s estimate is ¥8 trillion.
JCER also estimates that treating the contaminated water stored in hundreds of tanks at the plant will cost ¥20 trillion unless it is dumped into the ocean after being diluted as recommended by regulators.
Pourquoi le nucléaire est en train de ruiner la France Russian nuclear facility denies it is source of high radioactivity levels

Related Posts

Energia solar está prestes a atingir 100 gigawatts graças à China

غير مصنف

Energia solar está prestes a atingir 100 gigawatts graças à China

A indústria de energia solar está prestes a atingir um marco: as instalações globais deverão atingir 108 gigawatts este ano graças à China, mostram projeções da IHS Markit.

Will Cheap Renewables Make Nuclear Power Obsolete?

غير مصنف

Will Cheap Renewables Make Nuclear Power Obsolete?

Cheap renewables are mounting a serious challenge to nuclear power, which in 2017 has had a difficult year. Key projects have been abandoned, costs are rising, and politicians in countries which previously championed the industry are withdrawing their support.

غير مصنف

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

La compagnie japonaise d’électricité Kansai Electric Power a officialisé vendredi la fermeture en 2019 de deux de ses réacteurs nucléaires vieillissants. Elle juge trop élevé le coût de leur mise en conformité avec les nouvelles normes de sécurité post-Fukushima.

novembre 3, 2017

Japan Times: Real cost of Fukushima disaster will reach $626 billion — triple the government’s estimate

Informations

By: Japan Times

Real cost of Fukushima disaster will reach ¥70 trillion, or triple government’s estimate: think tank

A Tokyo-based think tank estimates that the complete cost of dealing with the Fukushima disaster could reach ¥70 trillion. | KYODO

 

A private think tank says the total cost of the Fukushima disaster could reach ¥70 trillion ($626 billion), or more than three times the government’s latest estimate.
In a study Saturday, the Japan Center for Economic Research said costs of dealing with the heavily damaged Fukushima No. 1 nuclear plant run by Tokyo Electric Power Company Holdings Inc. could rise to between ¥50 trillion and ¥70 trillion.
In December, the government estimated the costs would reach roughly ¥22 trillion.
“If costs rise, the public burden could greatly increase. The country’s nuclear policy needs to be reviewed,” JCER said.
The government’s initial expectations pegged the costs at ¥11 trillion.
But a study by the Ministry of Economy, Trade and Industry said that the final figure could turn out to be double the sum estimated in 2013.
Following that, the government decided to raise electricity rates to secure the money needed to cover compensation payments to the evacuees.
According to METI’s estimates, the bill for compensation payments will be ¥8 trillion, a figure the JCER decided to adopt.
The JCER, however, estimates the cost of the decontamination work will hit ¥30 trillion, or five times more than the government’s estimate of ¥6 trillion. The think tank based this calculation on a presumption that radioactive substances will be disposed of at a nuclear facility in the village of Rokkasho in Aomori Prefecture.
The government is seeking a way to treat radioactive soil and other waste in Fukushima Prefecture that could grow to roughly 22 million cu. meters, but where and how to dispose of it has yet to be decided.
Costs related to this procedure are not included in the government’s calculations.
In the meantime, JCER estimates that the cost of decommissioning the crippled reactors, which is expected to take 30 to 40 years, will reach ¥11 trillion. The government’s estimate is ¥8 trillion.
JCER also estimates that treating the contaminated water stored in hundreds of tanks at the plant will cost ¥20 trillion unless it is dumped into the ocean after being diluted as recommended by regulators.
Pourquoi le nucléaire est en train de ruiner la France Russian nuclear facility denies it is source of high radioactivity levels

Related Posts

Energia solar está prestes a atingir 100 gigawatts graças à China

Informations

Energia solar está prestes a atingir 100 gigawatts graças à China

A indústria de energia solar está prestes a atingir um marco: as instalações globais deverão atingir 108 gigawatts este ano graças à China, mostram projeções da IHS Markit.

Will Cheap Renewables Make Nuclear Power Obsolete?

Informations

Will Cheap Renewables Make Nuclear Power Obsolete?

Cheap renewables are mounting a serious challenge to nuclear power, which in 2017 has had a difficult year. Key projects have been abandoned, costs are rising, and politicians in countries which previously championed the industry are withdrawing their support.

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

Informations

Deux réacteurs nucléaires japonais fermeront définitivement en 2019

La compagnie japonaise d’électricité Kansai Electric Power a officialisé vendredi la fermeture en 2019 de deux de ses réacteurs nucléaires vieillissants. Elle juge trop élevé le coût de leur mise en conformité avec les nouvelles normes de sécurité post-Fukushima.

© Nuclear Free World 2017
Développé par Prima Estúdio